Message: this is our testing site. If you break it let us know (but don't break the live site)
Learn more nowMessage: this is our testing site. If you break it let us know (but don't break the live site)
Introduction to the Earthworks and Drilling section.
2 November 2023
The Earthworks and Drilling chapter manages the disturbance of land and associated discharges. Activities captured include:
These activities have previously been managed by the Regional Plan: Water for Otago (Water Plan). Plan Change 8 (Urban Topics), which was made operative on 3 September 2022, introduced new rules to the Water Plan for managing sediment from earthworks for residential development.
This chapter does not manage stormwater or discharges from contaminated land. These are covered in the Stormwater and Other Discharges chapters, respectively.
The table below provides a high-level comparison of the existing Water Plan provisions and the draft Earthworks and Drilling chapter and highlights the key changes from the Water Plan.
The table below provides a high-level comparison of the existing Water Plan provisions and the draft EARTH chapter and highlights the key changes from the Water Plan.
Earthworks and Drilling chapter of draft LWRP | Existing plan |
---|---|
Earthworks |
|
The existing permitted activity rule for earthworks now applies to all earthworks.
For earthworks to be permitted, they must not:
OR
OR
The setback distances in the above rules do not apply to earthworks for riparian planting. If the earthworks do not comply with the above permitted activity conditions, a discretionary consent will be required and, if granted, will require best practice sediment control measures to be undertaken in accordance with an erosion and sediment control plan. |
Rule framework for managing sediment discharges from residential construction only.
Earthworks are permitted if:
If earthworks do not meet all of the conditions listed above, a discretionary consent is required. |
Drilling |
|
Key changes: The drilling of land for purposes other than the construction of a bore is permitted if the drilling:
The drilling of a new bore, or drilling to alter or replace an existing bore, will require controlled consent, which will be granted if:
ORC will be able to set consent conditions on the following matters:
|
The drilling of land for purposes other than the construction of a bore is permitted if the drilling:
The drilling of a new bore requires consent as a controlled activity. ORC must grant consent but may impose conditions relating to:
|
Bores |
|
The use of an existing bore is permitted if:
If an existing bore does not comply with the conditions above, a controlled consent must be sought which may require the bore to be repaired or altered to ensure groundwater quality is protected. |
The use of an existing bore is currently not managed by the Water Plan. |
Site investigation |
|
The new framework supports the identification and recording of contaminated land by allowing site investigations to occur if they comply with the Contaminated Land Management Guidelines No. 1: Reporting on Contaminated Sites in New Zealand, (Ministry for the Environment, 2021), and are reported to ORC within 2 months of completion.
|
The disturbance of land for a site investigation to assess concentrations of hazardous substances is currently not managed by the Water Plan. |